We're finally able to see a little bit of light at the end of the tunnel, and we're pretty sure it's not a train coming back at us. We're in the stage now where everything is very exciting.

Our last update for the October and November progress was quite recent, so you probably don't need a refresher.

And, if you're interested, you can see all of my blog entries about the project, which started back in June.

The executive summary of the progress for these first 2 weeks of December is:
  • Shower walls and tile
  • Appliances "ready to go"
  • Deck poles and flooring
  • Cabinets
  • Mud sink
  • Countertops
  • Wet bar
  • Porch and deck railings


December 1, 2016 — Master shower walled in
Master shower walled in


December 1, 2016 — New kitchen sink, microwave, range, and dishwasher
waiting in the garage (amidst a good portion of the rest of our house
that's been "stored away" during this renovation and addition)

Kitchen sink, microwave, range, and dishwasher waiting the garage


December 5, 2016 — New deck poled and flooring started
Deck poles in and surface started


December 6, 2016 — Tiled-in master shower
Master shower tiled


December 9, 2016 — The first of the cabinets installation
Kitchen cabinets installed



December 15, 2016 — Deck and porch railings being installed
Deck and porch railings being installed



December 15, 2016 — Mud sink installed in laundry room
Mud sink installed in laundry room



December 16, 2016 — Countertops on the "fridge side" of our new galley kitchen
Counter tops on fridge side of galley kitchen



December 16, 2016 — Countertops on the "range/microwave/sink/dishwasher side"
of our new galley kitchen

Counter tops on range side of galley kitchen



December 16, 2016 — Eight 4-ft. tall by 2-ft. wide by 1-ft. deep pantry cabinets
with adjustable shelves

Pantry cabinets with adjustable shelves


December 16, 2016 — And we have a wet bar! (Well, it'll be wet after
the sink and faucet are installed. Bar fridge coming, too.)

Wet bar


December 16, 2016 — The rest of the railings on the (soon-to-be) screened-in porch
Screened in porch and deck railing completed


Coming soon: Back splashes, floors, appliances, and interior walls painting...

Comments

( 4 comments — Leave a comment )
(Anonymous)
Dec. 20th, 2016 12:33 am (UTC)
So exciting and updated!!
dailyafirmation
Dec. 20th, 2016 12:46 am (UTC)
Thanks!
(Anonymous)
Dec. 20th, 2016 08:39 am (UTC)
Can I come live with you? After its all done of course! FYI your bathroom looks just like mine. You two have very good taste😝
dailyafirmation
Dec. 20th, 2016 02:08 pm (UTC)
Ha!
Who is this?
( 4 comments — Leave a comment )

Profile

dailyafirmation
DailyAfirmation

Latest Month

February 2017
S M T W T F S
   1234
567891011
12131415161718
19202122232425
262728    

Page Summary

Tags

Powered by LiveJournal.com
Designed by Paulina Bozek